Status of clean tent integration and preparation
to complex tests of flight scientific payload of
Spectrum-X-Gamma mission at IKI test room

December 10,1998 - Laminar flow units were integrated to the clean tent at IKI test area.

November 15,1998 - Integration of the Clean tent at IKI test area is finished.

September 25,1998 - the clean tent laminar flow units (fLeicester University, UK) are put at IKI test room.

August 28,1998 - the clean tent supporting structure is assembled

August 6, 1998 - integration of the bottom level of the clean tent supporting structure